Before construction photo. Photos (1-11) follow in sequence.
February 2, 08 - 10:00 am Roof structure 50 % removed including old rear bathroom dormer.
February 2, 08 - 12:00 noon, Roof & gable walls completly removed. Missing floor framing & plywood flooring installed.
Feburary 2, 08 - End of day, all exterior walls pre-build, resting on floor & house completly covered with a 40' x 60' tarp.
February 3, 08 - 9:00 am Exterior walls 1/3 erected. Each section labeled to indicate location.
February 3, 08 - 11:00 am All exterior walls erected, plum and braced.
February 3, 08 - 2:30 pm Roof trusses 100 % erected, including gable ends
February 3, 08 - End of day, roof completly plywood and eventualty covered with tarp.
February 4, 08 - 12:00 noon Roof completly shingled and all windows installed. New second story addition completly water tight with wrap.
February 4, 08 - End of day, interior partitions erected, plum and braced. Plumber & Electrician started rough work in couple days.
Entire house & garage vinyl sided. 2nd story window over entrance door & shutters added for more curb appeal. Single window (left of entrance door) converted into double window.